Task Dependencies in Work Orders
From a Work Order record, planners can view and manage task dependencies within a Work Plan, between tasks across different Work Plans, and between Work Plan tasks and General tasks of the Work Order. This allows planners to define execution sequence and apply time offsets that control when a task must start or finish relative to its blocking task. This ensures tasks are executed in the correct order with controlled timing. For more information, see Task Dependency Management.
From a Work Order record, you can view and manage dependencies using the Dependency Manager tab or Custom Action Wizard Step.
* 
Ensure that the Work Order Dependency Manager custom LWC component is added to the Work Order or configured in the Custom Action Wizard step to view the Dependency Manager tab or wizard step. For more information, see Adding the Work Order Dependency Manager LWC Component to a Work Order and Creating a Custom Action for Work Order Dependency Manager.
The following topics are covered in this article: