• You cannot create Events for Crews.
• You cannot create Events for Resources associated with deactivated users. If you have a need to invite such users to Events, contact your Service Board system administrator.
• The maximum duration for Salesforce Events is 14 days. If you have a need to create Events longer than 14 days, contact your Service Board system administrator.
|
Section | Field | Description | ||
---|---|---|---|---|
Upper | NAME | Name for the Event. | ||
RELATED TO | Related Job, if applicable. | |||
TYPE | Event type: • Call • Email • Meeting • Overnight Stay • Other | |||
ASSIGNMENT | ASSIGNED TO RESOURCE | Resource assigned to the Event. Read-only when you click in a Resource row to create Events, or editable when you click the Create Event icon. | ||
ASSIGNED TO USER | Read-only field that is auto-populated based on the ASSIGNED TO RESOURCE value after Events are created and saved. | |||
SCHEDULE | ALL-DAY EVENT | Select this check box to create an all-day Event.
| ||
RECURRING EVENT | Select this check box to create a recurring Event and specify the following: • REPEAT: Select Daily, Weekly, Monthly, or Yearly. • REPEAT EVERY: Select the number of days between recurrences, from 1 to 31. • RECURRENCE START: Specify the date for the first recurring Event in the series. • RECURRENCE END: Specify the date after which Events no longer recur. | |||
EVENT START | Date and time when the Event starts. | |||
EVENT END | Date and time when the Event ends. | |||
LOCATION | LOCATION | Physical address where the Event is located. | ||
ADDRESS | Auto-populates with a city and map thumbnail based on the value in the LOCATION field. | |||
TRAVEL TIME TO LOCATION | Time required to travel to the Event location. Auto-calculated from the location for the assigned Resource to the Event location. | |||
TRAVEL TIME BACK FROM LOCATION | Time required to travel back from the Event location. Auto-calculated from the Event location to the next scheduled location for the assigned Resource. | |||
DESCRIPTION | Description of the Event. |
• When you click Create Event () on the Scheduler Calendar, Event start and end times are auto-calculated based on your current system time. When you double-click on Calendar rows for Resources, start times are set at the time where you click. In both cases, Event duration is based on the Default Event Duration field value in User Preferences. • If configured, Service Board automatically adjusts Event start times in cases where Travel Time to Location values for new Events conflict with scheduled times for previous Appointments or Events in the same work shift. |