By default, Appointments correspond to Salesforce Events. The maximum duration for Salesforce Events is 14 days. If you need to create Appointments longer than 14 days, contact your system administrator.
|
|
• You cannot bulk-dispatch Jobs to Crews.
• You cannot bulk-dispatch Jobs to Resources that are associated with deactivated users.
• Jobs in an end status or that were created from Projects are not supported for bulk dispatch.
• Bulk Job dispatch is supported only in the Scheduler tab, either from the currently selected Job List or from search results.
• When you select Jobs for bulk dispatch from multiple pages in the Job List or search results, and then drag and drop the Jobs from the currently selected page to a Resource row, the Jobs you selected on other pages remain selected, but are not dispatched.
• When Multi-Resource Scheduling is enabled and you bulk-dispatch previously assigned Jobs to different Resources, the Primary Resource check box is selected in all new Appointments and cleared in all previously created Appointments. Additionally, the Resource field value of all related Jobs is updated to the newly assigned Resource.
|
• The Dispatch Job dialog box can include editable settings for Appointments only, Jobs only, or both Jobs and Appointments. By default, this dialog box is disabled, and Crew appointments are not supported. • If configured, Service Board automatically adjusts Appointment start times in cases where Travel Time to Location values for new Appointments conflict with scheduled times for previous Appointments or Events in the same work shift. • If configured, you can click the Actual Time slider button to view live updates that show the actual times when technicians begin work on Appointments. You can then easily make adjustments when traffic conditions or unexpected situations cause delays. |