• Schedule Proposals may not work properly in cases where existing Appointments on the Calendar overlap. You can use this feature to optimize scheduling for up to 350 Jobs or 100 Project Tasks. Although these limits can be configured to other values, the maximum number of Jobs and Project Tasks cannot exceed these limits. Optimization for Crew Appointments is not supported.
• You can generate Schedule Proposals to simultaneously create new Appointments and reschedule existing open Appointments in non-end states.
• The Schedule Proposals option supports only previously unscheduled Dependent Jobs. Existing Appointments related to Dependent Jobs are not rescheduled.
• Schedule Proposals cannot be used to reschedule existing Multiple-Resource Jobs, Multiple-Appointment Jobs, and Dependent Jobs.
• Schedule Proposals do not support long-duration Project Tasks. When you invoke the Propose Schedule option for long-duration Project Tasks, the configured Default Appointment Duration value is not applied, and multiple Appointments are not created.
• The Propose Schedule menu option on the Resource Action Menu is available only for the Scheduler Resource List and in Resource search results. This option is not available for Resource recommendations or in the Multi-Assignment Calendar. Additionally, the Propose Schedule menu option is unavailable on the Map Resource List and Crew Resource List, for Resources that are inactive or related to inactive users, or in cases where the Enable Schedule Proposals setting is not configured.
|
• Service Board ships with one default scheduling policy, ServiceMax Optimization Setting. Your Service Board system administrator can deactivate this default policy or configure additional scheduling policies per your organization's needs. • If the currently selected Job List contains more than the maximum supported number of Jobs, for example, 350, in the Confirm Scheduling dialog box, a message asks you to confirm that you want to generate Schedule Proposals for only the first 350 Jobs. • If proposed time slots fall outside the currently selected date range, the view automatically adjusts to show them on the Scheduler Calendar. • To view Schedule Proposals that fall outside the current view or that are assigned to Resources that are hidden above or below the current view, click the More Proposals bars on the left, right, top, and bottom of the Scheduler Calendar. |
• On the Calendar, proposed rescheduled Appointments and their related tooltips appear in italic font. • After you edit proposed rescheduled Appointments, the Revert to Original and Revert to Proposal options become unavailable, and only the most recently edited version appears on the Calendar. • You cannot use Schedule Proposals to reschedule existing Appointments related to Multiple-Resource Jobs, Multiple-Appointment Jobs, and Dependent Jobs. |