Editing Task Dependencies in a Work Plan
You can edit an existing task dependency to update its relationship, associated tasks, or scheduling constraints in a Work Plan.
To edit a task dependency in a Work Plan:
1. From the Home page, go to the Work Plan Library tab.
The Work Plan Library page is displayed with the existing work plans.
2. Open a Work Plan.
3. Go to the Dependencies tab.
The list of dependent tasks and their related blocking tasks is displayed.
4. Click the task you want to edit.
6. Click Save.