Feature List
On the Features tab, you can manage which features are included when calculating insights for an area.
The following table lists the features which are included by default.
Feature Name
Display Name
Description
CurrentMaterial
Material
The material that was produced by the work center during the production block.
ShiftName
Shift
The shift that was active for the production block.
WorkCenterName
Work Center Name
The name of a work center.
DayOfWeek
Day of Week
The day of the week that is associated with the data.
isOvertime
Overtime
A boolean flag indicates whether the production block is overtime.
ShiftPrevious
Previous Shift
The shift prior to the current shift for the work center.
MaterialPrevious
Previous Material
The most recent previous material that was produced on the work center which does not match with the current material.
TimeIntoJobOrder
Time Into Job (Mins)
The amount of time into the current job order from the start of the job order until the start of the current production block.
TimeIntoShiftOrdinal
Time Into Shift
The amount of time into the shift when an event occurs. The values are displayed as 0 to 1 hour, 1 to 2 hours, 2 to 3 hours, 3 to 4 hours, 4 to 5 hours, 5 to 6 hours, 6 to 7 hours, 7 to 8 hours, 8 to 9 hours, 9 to 10 hours, 10 to 11 hours, 11 to 12 hours, or more than 12 hours.
TimeIntoCurrentMaterial
Time Into Material (Mins)
The amount of time that the current material has been in production on the work center. This value represents the time since the last material change on the work center.
TimeSinceLastPlannedDowntime
Time Since Last Planned Downtime (Mins)
The time in minutes since the last planned downtime event until the start of the current production block.
ActualAsPercentOfIdealCycleTimePB
Actual Cycle Time as Percent of Ideal Cycle Time
Indicates whether the work center is operating faster or slower than the ideal cycle time.
TimeLossScrapPrevious
Scrap Loss In Previous Production Block
The total time loss from scrap in the previous production block.
TimeLossUnscheduledPrevious
Unscheduled Loss In Previous Production Block
The total unscheduled time loss in the previous production block.
TimeLossPlannedDowntimePrevious
Planned Downtime Loss In Previous Production Block
The total time loss from planned downtime in the previous production block.
TimeLossUnplannedDowntimePrevious
Unplanned Downtime Loss In Previous Production Block
The total time loss from unplanned downtime in the previous production block.
TimeLossSpeedLossPrevious
Speed Loss In Previous Production Block
The total time loss from speed loss in the previous production block.
TimeLossSmallStopsPrevious
Small Stop Loss In Previous Production Block
The total time loss from small stops in the previous production block.
TimeLossChangeoverPrevious
Changeover Loss In Previous Production Block
The total time loss from changeover in the previous production block.
TimeLossUnknownPrevious
Unknown Loss In Previous Production Block
The total time loss from unknown reasons in the previous production block.
ShiftChangeInNextPB
Shift Change Next Production Block
A planned shift change in the next production block.
The following table lists the features which are excluded by default.
Feature Name
Display Name
Description
TimeLossCurrentPB
Time Loss In Current Production Block
The total time loss for all loss types in the production block. Includes all production, availability, and loss events.
TimeLossScrapCurrentPB
Scrap Loss In Current Production Block
The total time loss from scrap in the current production block.
TimeLossUnscheduledCurrentPB
Unscheduled Loss In Current Production Block
The total time loss from unscheduled time in the current production block.
TimeLossPlannedDowntimeCurrentPB
Planned Downtime Loss In Current Production Block
The total time loss from planned downtime in the current production block.
TimeLossUnplannedDowntimeCurrentPB
Unplanned Downtime Loss In Current Production Block
The total time loss from unplanned downtime in the current production block.
TimeLossChangeoverCurrentPB
Changeover Loss In Current Production Block
The total time loss from changeover in the current production block.
TimeLossUnknownCurrentPB
Unknown Loss In Current Production Block
The total time loss from unknown reasons in the current production block.
TimeLossSpeedLossCurrentPB
Speed Loss In Current Production Block
The total time loss from speed loss in the current production block.
TimeLossSmallStopsCurrentPB
Small Stop Loss In Current Production Block
The total time loss from small stops in the production block.
TimeLossUnaccountedTimeCurrentPB
Unaccounted Loss In Current Production Block
The total unaccounted time loss in the current production block.
TimeLossUnaccountedTimePrevious
Unaccounted Loss In Previous Production Block
The total unaccounted time loss in the previous production block.
TimeIntoShift
Time Into Shift (Mins)
The amount of time into the current shift from the start of the shift until the start of the current production block.
IdealCycleTime
Ideal Cycle Time (Time in seconds to produce one unit)
The ideal cycle time for the material.
JobRestartedCurrentPB
Job Restarted in Production Block
A boolean value indicates whether a job order was restarted for the current production block.
epochPBStartTime
Date and Time
The date and time when the production block started. It provides information about the losses that most often occur during a specific time period.
epochPBEndTime
Production Block Epoch End Time
The end time of the production block in epoch format.
CountProductionEventsInPB
Production Event Count
The count of production events in the current production block.
CountProductionEventsInPreviousPB
Production Event Count In Previous Production Block
The count of production events in the previous production block.
UnitsProducedInProductionBlock
Units Produced
The number of units produced in the production block.
NumberOfUnitsToBeProduced
Number of Units Expected
The planned number of units to be produced in the production block.
ProductionBlockDuration
Duration of Production Block
The duration of the production block.
JobCountLastShift
Job Count Last Shift
The total number of jobs executed on the work center in the previous shift.
JobCountLastDay
Job Count Last Day
The total number of jobs executed on the work center in the previous day.
JobCountLastWeek
Job Count Last Week
The total number of jobs executed on the work center in the previous week.
ProductionBlockUID
Production Block UID
The unique identifier for the production block.
WorkCenterUID
Work Center UID
The unique identifier for a work center.
ProductionBlockStartTime
Production Block Start Time
The start time of the production block.
ProductionBlockEndTime
Production Block End Time
The end time of the production block.
JobPausedAtEndofCurrentPB
Job Paused At End of Production Block
A boolean value indicates whether the current production block is ending due to a job order being paused.
Additional features can be added, which are excluded by default. For more information, see Adding Additional Features for Calculating Insights.