OptiMax Status
This field shows the Schedule Optimization scheduling status for the work order. The following table lists the possible values and describes their meaning.
* 
The OptiMax Status field value is updated for RTO only.
Value
What It Means
OPT_INITIATED
Scheduling job is initiated for the work order.
OPT_QUEUED
The work order is queued for scheduling.
OPT_PENDING
The work order is not taken up for scheduling.
OPT_TENTATIVE
Schedule Optimization has started the process of scheduling the work order. Scheduling information in the work order, if any, is tentative. Scheduling is not finalized yet.
OPT_ERROR
Schedule Optimization is encountering an error while trying to schedule the work order currently. The corresponding error is updated in the OptiMax Error Text field.
OPT_SKIPPED
Work order is skipped because Preferred Start Time and Preferred End Time are outside the dispatch horizon.
OPT_COMPLETED
The work order is assigned to a technician.
OPT_UNASSIGNED
The work order is unassigned because of violations of hard constraints.
OPT_BATCH
The work order is batched.
Processing Complete
Scheduling is complete for the work order. This is applicable only for Batch Optimization.