Field
|
Description
|
|---|---|
|
Enable Dynamic Adjustment
|
Select this checkbox to configure Dynamic Adjustment to reschedule the future PM visits of PM Plans based on the early or delayed PM completion of the current PM Work Order. For more information, see Performing Dynamic Adjustments for PM Plans.
|
|
Work Order Completion Basis
|
Dynamic Adjustment considers a PM Work Order to be complete based on the selected Work Order date or time field.
|
|
Activity Work Order
|
Select First or Last to determine whether Dynamic Adjustment performs adjustments on the first or last update to the Work Order field specified in Work Order Completion Basis. The system tracks activity behavior across multiple Work Orders when generating one Work Order per Installed Product coverage.
|
|
Adjustment Range
|
Specifies the minimum and maximum horizon for Dynamic Adjustment in PM Schedules. If a PM Work Order is completed below the minimum value, no adjustment occurs. If completed above the maximum value, the adjustment is limited to the maximum value.
|
|
Type
|
The Adjustment Type defines how Dynamic Adjustment is applied:
• Actual: Adjusts the next Scheduled On date based on the actual difference between the Work Order Completion Basis date and the Preferred Start date of the last completed Work Order.
• Fixed: Adjusts the next Scheduled On date by a fixed value specified in the Adjustment Value and Adjustment Unit fields.
|
|
Adjustment Value
|
When Adjustment Type is Fixed, this field indicates the fixed adjustment value applied by the dynamic adjustment logic.
|
|
Adjustment Unit
|
When Adjustment Type is Fixed, this field indicates the fixed adjustment unit applied by the dynamic adjustment logic.
|