Initial DPM Administration Activities
After
your data has been imported and before making
DPM available to users, an administrator must complete the following activities in
Administration:
1. Ensure that your materials are present as expected. You can create new materials as needed. For more information, see
Materials.
2. Ensure that reason trees are assigned to your equipment and materials as expected. You can create new reason trees and update assignments as needed. For more information, see
Reason Trees.
3. Ensure that calendars are assigned to your equipment as expected. You can create new calendars, including creating new shifts and shift schedules, update the shifts and shift schedules for your existing calendars, and update the equipment assignments as needed. For more information, see
Shifts and Calendars.
4. Ensure that the production block duration is set appropriately for each site in your equipment list. For more information, see
Site Configuration Tab.
5. Ensure that materials are added to the work centers that produce them, and the material settings are appropriate for each work center. For more information, see
Materials List Tab.
6. Ensure that the production settings are appropriate for each work center. For more information, see
Production Settings Tab.
8. Set the target values and status thresholds for the metrics used in
Scorecard, as required. In addition to Scorecard, Production Dashboard and Performance Analysis also use the status threshold values for the
Production OEE metric to determine OEE colors. For more information, see
Target Definition Tab and
Status Threshold Tab.
9. Optionally create job orders. For more information, see
Job Orders.
10. Grant permissions to Production Dashboard users. All users have permission to delete manually entered loss events and edit manually entered and automated loss events for the first 24 hours after they are entered. After the first 24 hours, only users who have been granted permissions can delete manually entered loss events or edit manually entered and automated loss events. For more information, see
Granting User Permissions for Editing and Deleting Loss Events.
The following activities can be completed after DPM has been in use over time:
1. Optionally set up pipeline schedules for each of your areas. The pipeline schedules push data that is analyzed for the
View Loss Insights action in
Performance Analysis. This setup step can be performed later, after DPM has been in use and production data has been gathered. At least one month of data (or more than 500 production blocks) is needed for repeating patterns and scenarios to be identified. For more information, see
Time Loss Analytics.
|
If multiple enterprises were imported during data import, ensure that the name of the correct enterprise is configured. Only one enterprise can be configured, and only data for the configured enterprise is available in Production Dashboard and throughout DPM.
To configure the enterprise, complete the following steps in ThingWorx Composer:
1. Navigate to the PTC.MfgModelImpl.Manager Thing and click Edit. 2. Under Configuration, scroll to the NetworkConfiguration configuration table and click in the table row. 3. In the edit window, enter the Thing name of the network entity for the enterprise in the network field. This is the Thing name that was specified for the enterprise when the data was imported. Do not change the value of the id field. 4. Click Set to close the edit window. 5. Click Save to save the configuration changes. |