The displayed values for the ideal cycle time and best demonstrated speed are rounded off to a single decimal place. The calculation comparing the two values considers the complete value. For example, both a best demonstrated speed of 17.389 and an ideal cycle time of 17.401 display as 17.4, but the alert () displays because the best demonstrated speed of 17.389 is faster than the ideal cycle time of 17.401. |
Existing job orders for this material on this work center are not updated with the new ideal cycle time. If you want job orders that have not yet started production (in the Pending or Dispatched states) to use the updated ideal cycle time, cancel the existing job orders and create new ones. The new job orders will reflect the updated ideal cycle time for the material. Job orders that have already completed or are in production (in the Running or Held states) correctly use the previous ideal cycle time. |