If the plan is in auto-execution mode, the availability of several actions depends on the project, plan, and activity state. For more information, see Plan States and Available Actions.
The availability of actions also depends on your access. For more information, see Understanding Data Accessibility.
|
Assign one or more resources to the activity.
Resources track work associated with the activity.
|
|||
If you have been assigned as a resource to multiple plan objects, select the checkboxes next to those activities and then select
> to track work for several resource assignment tasks at once. |
|||
Edit the project plan in Microsoft Project.
|
|||
Insert Sub-plan Above |
Create a subplan to inserte above the selected activity or subplan.
|
||
Insert Sub-plan Below |
Create a subplan to inserte below the selected activity or subplan.
|
||
Insert Sub-plan as a Child |
Create a subplan as a child for the selected activity. The selected activity is updated to indicate that it is a summary activity, reflecting the work, cost, and status information of subplan.
|
||
Edit the selected activities.
|
|||
Export as Template |
Export the plan as a template. This creates a ZIP file that you can save to your local machine.
|
||
Export the plan to Microsoft Project.
|
|||
Import a plan from Microsoft Project.
|
|||
Increase Indent |
Move the selected activity down a level within the plan, indicating that it is a child activity or sub-task to another activity.
For example, to indicate that one activity is comprised of several smaller tasks, indent those tasks below the larger activity. Those tasks become child activities, and the larger activity is converted to a summary activity.
The summary activity is updated to reflect the work, cost, and status information of any activity indented beneath it.
Increasing indent of an activity in an executing summary activity does not change the actual start date of the summary activity.
|
||
Create an activity to be inserted above the selected activity.
|
|||
Create an activity to be inserted below the selected activity.
|
|||
Create a child activity for the selected activity. The selected activity is updated to indicate that it is a summary activity, reflecting the work, cost, and status information of the child activities.
For more information about summary activities, see Summary Activity Calculation.
|
|||
Paste an activity or subplan above the selected activity.
|
|||
Paste an activity or subplan below the selected activity.
|
|||
Paste an activity as a child activity for the selected activity. The selected activity is updated to indicate that it is a summary activity, reflecting the work, cost, and status information of the child activities.
For more information about summary activities, see Summary Activity Calculation.
|
|||
Create a new activity in the plan. The new activity is created below the selected plan object or at the end of the plan if an object is not selected.
|
|||
New Sub-plan |
Create a new subplan in the plan. The new subplan is created below the selected plan object or at the end of the plan if an object is not selected.
|
||
Create a new deliverable to associate with the activity. The availability of this action depends on the activity type and whether the Link deliverables with project activities option is selected when the project is created.
|
|||
Capture the attributes of all plan objects in a baseline.
|
|||
Create up to five activities at a time. This applies only to plan activities.
|
|||
Decrease Indent |
Move a child activity (an activity indented below a summary activity) up a level within the plan. For example, if a summary activity contains a child activity that is no longer associated with the summary activity work, you can decrease the indent of that child activity to make it independent.
When you decrease the indent of a plan object, the scheduling information for the summary activity is updated to reflect the removal of that child activity.
|
||
Start Execution |
Manually start a plan.
You can execute a scheduled manual plan using this action when the property com.ptc.projectmanagement.plan.startManualPlan, in wt.properties file, is true. The default is false.
|
||
Save as Template
|
Save the plan template and add it to the Templates table. These templates are available from the Plan Templates view at the site and organization levels.
|
||
Set the status, risk, and track the number of work hours or percentage of work completed for the selected activity. • The track work icon appears in the Assignments column when you have been assigned to the activity as a resource. Click this icon to open the Track Work for Selected Assignments window, where you can track work related to your resource assignment task. • If you are a project manager or the owner of an activity, select Track Work from the right-click actions menu. The Track Work window opens, where you can track work related to the activity. If resources have also been assigned to the activity, any actual work you enter is distributed evenly between the resource assignment tasks. |
|||
View a graphical display of how resource time is allocated.
|
|||
View the plan in the Gantt chart viewing tool.
|
Complete the selected activity.
The % Work Complete is automatically set to 100 and the Actual Work field is updated to reflect all work hours have been completed.
|
|||
Manually complete the plan. You cannot restart a plan that has been completed.
|
|||
If the activity has been suspended, this action resumes execution.
|
|||
If the plan has been suspended, this action resumes execution.
|
|||
Manually start an activity or milestone.
|
|||
This action initiates automatic execution of the plan.
|
|||
Pause the selected activity. You cannot track work for a suspended activity. A subplan cannot be suspended . You can only suspend the reference plan or activiity, not the subplan.
|
|||
Pause plan execution. No tasks can be completed and delivery of subsequent tasks is prevented until planning or resource issues are resolved.
|
|
You cannot increase indent or insert an activity or a sub plan in an executing or a completed plan activity.
The last remaining plan activity, sub plan activity, or summary activity cannot be deleted from an executing plan.
|