Windchill supports both MPP and XML files. You can only select XML files that were generated according to the Microsoft Project 2003, 2007, or 2010 XML format.
|
|
Selecting Replace also removes objects that are not supported in Microsoft Project. For example, any deliverables included in your plan will be deleted.
If you are importing a plan using Replace mode, then the reference to the subplan is dropped.
|
|
• If you are importing a plan created in Microsoft Project, ensure that all activities have their task mode set to Auto Scheduled. Activities with the Manually Scheduled mode will be auto-scheduled when imported back into Windchill ProjectLink, which might create confusion.
• The actual start date in the Microsoft Project plan should match the actual start date in Windchill or a later date. The import fails if the actual start date in Microsoft Project plan is prior to the actual start date in Windchill. • When a manual plan is started using the Start Execution action, if the tracking attributes of the plan are modified in Microsoft Project plan but the plan has not started in Windchill, the import fails. |