Deployed milestone (UPDM - MODAF aliases)
Creation
To create a Deployed Milestone:
◦ Click the
Deployed Milestone button, and then click in free space on the diagram. On the Select Type dialog, create or select the
Project Milestone element that is the classifier of the Deployed Milestone.
◦ From an appropriate Modeler pane, locate the
Project Milestone element that you want to use as the classifier of the Deployed Milestone, and then drag that Project Milestone to free space on the diagram. From the dialog, select Deployed Milestone, and then click OK.
After creating a Deployed Milestone you can set its date and values: right-click the Deployed Milestone, point to Set, and then click Date or Values as appropriate.
Appearance
Relationships
The following relationships are of importance to a Deployed Milestone:
•
Milestone Sequence relationships link a Deployed Milestone to the milestone elements that are predecessors and successors to that Deployed Milestone. The predecessor and successor elements can be Actual Project Milestone, Deployed Milestone, Increment Milestone, No Longer Used Milestone and Out Of Service Milestone elements.
• Link a Deployed Milestone to its resources. To create this relationship: right-click the Deployed Milestone, point to Links, and then click Resource.
The following sections provide information about how a Deployed Milestone is used in the model.
Create a Deployed Milestone from
Create from a Deployed Milestone
Shown on these diagrams, tables and matrices
UPDM writeable properties
The following writeable properties are available on the Deployed Milestone tab of a Deployed Milestone element's Property Pages:
• URI