Increment milestone (UPDM - NAF aliases)
Creation
To create an Increment Milestone:
From an Architectural Description or Service Description: right-click the Architectural Description or Service Description, point to New, point to NAF, point to Programme, and then click Increment Milestone.
On the Select Type dialog, create or select the Project Milestone that is the classifier for the Increment Milestone.
Click the Increment Milestone button, and then click in free space on the diagram. On the Select Type dialog, create or select the Project Milestone element that is the classifier of the Increment Milestone.
From an appropriate Modeler pane, locate the Project Milestone element that you want to use as the classifier of the Increment Milestone, and then drag that Project Milestone to free space on the diagram. From the dialog, select Increment Milestone, and then click OK.
After creating an Increment Milestone you can set its date and values: right-click the Increment Milestone, point to Set, and then click Date or Values as appropriate.
You can convert an Increment Milestone to an Actual Project Milestone, Deployed Milestone, No Longer Used Milestone or Out Of Service Milestone: right click the Increment Milestone, point to Convert To, and then click the required command.
Appearance
When shown on an NPV-3 Actual Project Definition, an Increment Milestone appears as follows:
When shown on an NPV-2 Programme Timelines, an Increment Milestone appears as follows:
Relationships
The following relationships are of importance to an Increment Milestone:
Milestone Sequence relationships link an Increment Milestone to milestone elements that are predecessors and successors to that Increment Milestone. The predecessor and successor elements can be Actual Project Milestone, Deployed Milestone, Increment Milestone, No Longer Used Milestone and Out Of Service Milestone elements.
The following sections provide information about how an Increment Milestone is used in the model.
Create an Increment Milestone from
Create from an Increment Milestone
Only the UPDM elements that can be created from all UPDM elements (Alias, Definition, Information and Metadata).
Shown on these diagrams, tables and matrices
In addition to the NAV-2 Integrated Dictionary and NTV-1 Standards Profile, which can show all UPDM elements:
UPDM writeable properties
The following writeable properties are available on the Increment Milestone tab of an Increment Milestone element's Property Pages:
URI