指标 | 公式 |
---|---|
生产 OEE | Total Effective Time / Total Production Time |
可用 OEE 总计 | Total Effective Time / (total number of hours in the date range * number of work centers in the filtered equipment) |
损失小时数总计 | Planned Production Time + Overtime - Total Effective Time |
平均产能 | Production Quantity / Total Production Time |
产量 | Total quantity of good materials produced |
损耗率 | Total count of scrapped materials / (Production Quantity + total count of scrapped materials) |
完成的作业 | Number of completed job orders |
计划的作业 | Number of job orders that are scheduled + number of job orders that are completed |
计划的生产时间 | (Total number of hours in the date range * number of work centers in the filtered equipment) - Overtime - time outside of a scheduled shift |
加班 | Time in production outside of a scheduled shift + time during overtime shifts |
生产时间总计 | Planned Production Time + time spent in production outside of a scheduled shift |
有效时间总计 | Good Count * Ideal Cycle Time |