Open the Track Work window for the activity. Enter a value into the Actual Work field or the % Work Complete field.
|
|
If an activity has resource assignments, then an assigned resource can start the activity by tracking work for their resource assignment task. Open the Track Work for Selected Assignments window and enter a value into the Actual Work, % Work Complete, or Remaining Work field.
|
|
Start |
This action is only available in automatically executed projects, and it appears for activities that have not yet started but do not have any obstacles (such as a predecessor or constraint type) that would prevent the activity from starting.
|
Automatic
|
In automatic execution mode, activities automatically start when they reach their Estimated Start date.
|
|
For the following activities, the actual start date rolls up to the parent summary activity and plan:
• The first direct child activity of a summary activity
• The first child summary activity
• The first child subplan
|