|
When you complete an activity, the Actual Work value is updated to match the Estimated Work value. This behavior is controlled by the Keep Actual Work preference. To update the Work value instead, set this preference to Yes.
|
|
The following status indicators appear when an activity has been completed: • Completed—Completed on or before the deadline. This indicator also appears when no deadline is set. • Completed Late—Completed after the deadline. • Canceled—This indicator appears when an incomplete activity has been canceled due to a change in plan or project state. This indicator only appears in automatic execution plans. For more information, see Automatic Execution. |
Open the Track Work window for the activity. Enter 100 into the % Work Complete field, or enter a value into the Actual Work field that is equal to or greater than the amount of work required for the activity.
|
|
If an activity has resource assignments, then the activity is complete when all associated resource assignment tasks have been completed.
To manually complete a resource assignment task, open the Track Work for Selected Assignments window and enter 100 into the % Work Complete field. Alternatively, you can also enter 0 into the Remaining Work field or enter a value into the Actual Work field that is equal to or greater than the amount of work required for the assignment.
|
|
Complete |
The Complete action appears in the following situations:
• From the right-click actions menu of resource assignments in the Tasks table. (Manual and automatically executed projects.)
• From the right-click actions menu of in-process activities in the Tasks table and the Schedule table. (Automatically executed projects only.)
The % Work Complete is automatically set to 100 and the Actual Work field is updated to reflect all work hours have been completed.
|