Complexity
|
Description
|
Fast Track Change Request
|
Fast track change requests have low impact and cost, and therefore, can be processed quickly through the change process. The cost threshold for changes that can be processed using the fast track changes is typically set by company policy.
|
Full Track Change Request
|
Full track change requests are those with a high impact and cost and that require close analysis and review. Full track changes must pass through the change review board (CRB) prior to implementation.
|
Complexity
|
Description
|
Fast Track Change Notice
|
Fast track change notices have low impact and cost, and therefore, can be processed quickly through the change process. The cost threshold for changes that can be processed using the fast track changes is typically set by company policy.
|
Full Track Change Notice
|
Full track change notices are those with a high impact and cost and that require close analysis and review. Full track changes must pass through the change implementation board (CIB) prior to implementation.
|
Basic Change Notice
|
Basic change notices are corrective or administrative and do not require justification and approval through the change request process. Basic change notices can also be used to document changes being released from design partners or suppliers, or they can be used to document changes prior to the formal change control process. The use of basic changes is typically set by company policy.
|