Additional Windchill Capabilities > Manufacturing Process Management > Working with Manufacturing Resources > Inserting an Existing Resource
  
Inserting an Existing Resource
You can insert an existing resource into another resource hierarchy (for example, to add a work center to a plant, or to add a part as a resource).
To insert an existing resource
1. In the Manufacture Resource Browser select the resource you would like to add an existing resource to.
2. Click the insert existing resource icon .
A search window opens.
3. Select options from the Context Type, Context Name, and Type drop-down lists.
4. Enter the search criteria, and click OK.
The results of the search are returned at the bottom of the window.
5. Select the desired object, and click OK.
The selected object appears in the explorer window.