Integrations (PTC products, 3rd party products and code) > PTC product integrations (Asset Library, Lifecycle Manager, Reviewer, Windchill & ThingWorx) > PTC Integrity Lifecycle Manager > Synchronizing a model and PTC Integrity Lifecycle Manager document > Synchronizing using the settings from an Integration for Lifecycle Manager mapping (Integration for PTC Integrity Lifecycle Manager)
  
Synchronizing using the settings from an Integration for Lifecycle Manager mapping (Integration for PTC Integrity Lifecycle Manager)
1. From Modeler, open the model that owns the Packages that you want to synchronize.
2. On the Tools menu, point to Integrity Lifecycle Manager, and then click Synchronize.
3. On the Mapping Selection page, select the check boxes associated with the Integration for Lifecycle Manager Mappings you want to use.
4. Click the Synchronize button.
5. Click the Synchronize Only button.
6. On the Synchronization Log page, review the log for any problems that occurred during the synchronization.