Mesure | Formule |
---|---|
TRG production | Total Effective Time / Total Production Time |
TRG disponible total | Total Effective Time / (total number of hours in the date range * number of work centers in the filtered equipment) |
Heures de perte totales | Planned Production Time + Overtime - Total Effective Time |
Débit moyen | Production Quantity / Total Production Time |
Quantité de production | Total quantity of good materials produced |
Taux de rebut | Total count of scrapped materials / (Production Quantity + total count of scrapped materials) |
Nombre d'ordres terminés | Number of completed job orders |
Nombre d'ordres planifiés | Number of job orders that are scheduled + number of job orders that are completed |
Temps de production planifié | (Total number of hours in the date range * number of work centers in the filtered equipment) - Overtime - time outside of a scheduled shift |
Heures supplémentaires | Time in production outside of a scheduled shift + time during overtime shifts |
Temps de production total | Planned Production Time + time spent in production outside of a scheduled shift |
Temps effectif total | Good Count * Ideal Cycle Time |