Create a Resource Assignment
You create a resource assignment when you assign a resource to an activity.
You can assign one or more resources to a plan activity, thereby factoring resource costs into the overall plan budget and automatically assigning tasks to team members. For more information, see
Resource Assignments.
|
• You cannot assign resources to summary activities or deliverables. If the Link deliverables with project activities option is selected when the project or program is created, you cannot assign resources to a milestone.
• If the plan is in auto-execution mode, you cannot assign a resource to activities in the In Process or Completed states. For more information, see Auto-Execution State and Available Actions.
|
When using the
Assign Resources action, the resource units are automatically calculated from the value of the
Max Units property. For more information, see
Resource Attributes and
Activity Schedule Calculation.
1. There are several ways to assign a resource to a plan activity:
◦ When
creating or
editing an activity, use the options available under the
Resources field.
◦ From the
Schedule table, select
Assign Resources from the right-click actions menu of a plan activity.
◦ From the
Tasks table, select
Assign Resources from the right-click actions menu of a plan activity.
2. Under Resources, select a resource using one of the following methods:
◦ Begin entering a resource name into the Search by Name field. An auto-populated list appears below as you type. You must enter at least three characters.
◦ Click
Search or the add icon
to open a new window from which you can select from all project resources filtered by type.
◦ To remove a resource, select the resource and click the remove icon
.
3. In the Assignment Type field, select one of the following:
◦ If the resource is a Windchill User or Other type, then this field is set to Single and cannot be changed.
◦ If the resource is a Windchill Group or Windchill Team Role type, then you can select from the following options:
▪ Pool—Work is initially assigned to all users included in the group or role. When one user accepts the work, the corresponding assignment is removed from the assigned tasks of the other users.
▪ Bulk—Work is split evenly between all members of the resource group or role. A distinct assignment is created for each user.
▪ Shared—Work is assigned to all members of the resource group or role. Members complete work as they are able, and their work is added towards the overall completion status. One or more assignees can complete work; however, not all assignees are required to complete a task.
| To automatically create a resource assignment task when a new activity is created, set the > preference to Yes. If a resource is not assigned to the activity, then a default resource assignment is created for the activity owner. If no owner is assigned to the activity, then the activity creator is assigned as a resource. For more information, see Preference Management. |