• To import and export plans, your version of Microsoft Project must be compatible with Windchill. For more information, see “Windchill Client Components” in the see Windchill 11.0 Software Matrices.
• If the Microsoft Project plugin fails to function, check your config.xml file. The LogLocation attribute must be defined with a valid directory name. You must also have create and edit permission within the directory location.
This is necessary to save any errors or warnings generated by the Windchill server.
|
Microsoft Project
|
Windchill Project
|
|
---|---|---|
Terms
|
• Task
A Microsoft Project “task” is the same as a Windchill activity.
• Assignment
A Microsoft Project “assignment” is the same as a Windchill task.
|
• Activity
A Windchill activity is the same as a Microsoft Project “task.”
• Task
In Windchill, a task is a work item is assigned to users either automatically or as part of a generated workflow. For more information, see Managing Your Tasks.
|
Milestone behavior
|
Milestones can be associated with child milestones or activities.
|
Milestones cannot be associated with child milestones or activities.
|
Deliverables
|
Deliverable objects are not supported in Microsoft Project.
|
Windchill deliverables are objects that can be associated with activities and milestones. For more information, see Deliverables.
|
Calendar
|
Uses separate calendars associated with the project or program as a whole and with each resource in the project or program
|
Uses a single system calendar for all schedule and cost calculations across all projects or programs and all resources.
|
Resources
|
Exposes overtime rates for resources, and calculates total costs at start or finish.
|
Does not expose overtime rates for resources, and all costs are immediately calculated when entered.
|