Gantt Explorer
To view your plan in the Gantt explorer, navigate to the Schedule table and select Actions > View in Gantt Explorer or click Gantt Explorer icon on the table toolbar.
The Gantt chart consists of a dual-pane panel: the left pane is the structure pane, and displays the subplans, plan activities, milestones, and summary activities in a tree table, the right pane shows a graphic display of the time dependence between the plan elements.
* 
You can view multiple projects in the Gantt explorer at one time. Navigate to the Projects, Programs, or Products table. Select one or more contexts and then click .
* 
Selecting multiple projects in the Projects table does not show all the plans under the projects in the Gantt explorer. If you want to view multiple plans, navigate to the Plans table, select the required plans, and then click .
The Gantt explorer toolbar allows you to change your view to better analyze the project plan:
Navigate forward and backward through time spans.
Expand and collapse summary activities to view or hide child activities.
Increase or decrease the scale of the graphic display of the project plan. Zooming out allows you to view the entire project plan over a long period of time
Adjust the time span to view to complete plan.
View the Gantt explorer in full screen mode.
Update the Gantt explorer information.
Displays the critical path of the project plan. The critical path highlights the tasks required to complete the project plan. When the last task on the critical path is finished, the project is also finished.
Open a new window with a graphical representation of how resource time is allocated. For more information, see Capacity Report.
Table Views
Select a table view to view different attributes for each plan object. Table views correspond to those available in the Schedule table.
Isto foi útil?