Viewing the Impact
After the change task is created, you can view the:
Change tasks that impact a baseline in the Impacted By Objects table on the information page of a baseline.
Baselines that are impacted by the change task in the Impacted Objects table on the information page of a change task.
* 
The tables are not visible by default. You need to configure the pages to display the tables. For more information, see Customizing Information Page Tabs.
Additionally, you can view the Impacted Objects table while completing or auditing a change notice. However, you need to configure the Complete Change Notice Task or Audit Change Notice template to display the table. For more information, see Using Custom Task Form Templates.
You can view the impact of a change task on a baseline member in the Impact Intent column. You can customize the following user interface areas to display this column:
Resulting Objects table on the information page of a change task
Change Summary table on the information page of a change notice
Complete Resulting Objects table on the Complete Change Notice Task page
Review Resulting Objects table on the Review Change Notice Task page