|
When publishing a Process Plan with an operation, there must be a work center, with a department, assigned to the operation. The work center should also have time values attributed to it, to allow for the creation of activities. If there are no time values attributed to the work center then no activities are created. To schedule resources the Unit of Measure (UOM) for the resource should be set to Hour (HR). In addition, the resource group to which the processing resources and work centers belong should also be used.
|
Process Plan Attribute
|
Oracle Applications Routing Attribute
|
Revision
|
Revision of the Routing
|
Distribution Target
|
Organization
|
Parts
|
Item number
|
Operations
|
Operations
|
Resources
|
Resources
|
Windchill Operation Attribute
|
Oracle Manufacturing Operation Attribute
|
Description
|
Description
|
Operation Label
|
Operation Sequence
|
ERP validation Code
|
Not mapped
|
Scheduled
|
If equal to Yes, this means the Work Center Scheduled allocation in Oracle is set to Yes. If set to No, then the Work Center scheduled allocation is set to No.
|
Department
|
Department
|
Work Center
|
Resources for all non-zero times defined in the operation.
|
Processing Resources
|
See section Consumable Resource Allocations for Operations
|
Allocated Parts
|
See section Operation Allocated Parts.
|
Windchill Operation Allocated Part Attributes
|
Oracle Manufacturing Attribute
|
Assembly Part Number
|
Bills Of Material that needs to be created/changed for assigning the operation sequence number to its component.
|
Component Part Number
|
Component Number to which the operation sequence is applied.
|
Operation label of associated Operation number
|
Allocated Component’s Operation Sequence Number
|
|
Processing resources must exist in the Oracle Applications system.
|
Windchill Consumable Resource
Allocations Attribute
|
Oracle Manufacturing Attribute
|
Number
|
Resource code
|
Usage rate
|
Usage rate
|
Scheduled flag
|
Scheduled (Yes or No)
|
|
A control characteristic that is associated to an operation will be published upon publishing the holding process plan, provided the distribution target attribute Publish Control Characteristics when Publishing a Process Plan has a value of Yes; this happens even if the control characteristic is associated to a part as well and the attribute Publish Control Characteristics when Publishing a Part has a value of No.
|
|
If a model item’s EPM document is not associated to the owner of the holding control characteristic, an attempt to publish the control characteristic results in a failure.
|
|
Windchill ESI publishes a control characteristic to the same distribution targets as those associated to the holding part or process plan.
|
|
Although control characteristics and their associations are sent with the ESI response, these are ignored by the EAI software components.
|