Data Management Capabilities > Managing Change > About Effectivity > Changing the Effectivity of an Object
  
Changing the Effectivity of an Object
You can change effectivity from the following locations:
Implementation Plan table of a change notice
Resulting Objects table of a change task
Affected Objects table of a variance
Information page of those objects that can be effectivity-managed, only by users that have administrative capabilities
Use the following procedure to change the effectivity of an object:
1. Click the set effectivity icon .
The Set Effectivity window appears, with selected effectivity-managed objects listed in the Set Effectivity table. From this table, you have the following options:
Add a new effectivity statement for the listed effectivity-managed objects.
Update an existing effectivity value, by modifying the existing effectivity.
Delete an existing effectivity statement, by selecting the Delete icon for the effectivity statement of the selected object.
2. Perform one of these activities and then click OK to return.