Unsupported Feature
|
Error or Warning
|
Resolution in Microsoft Project
|
Schedule From
|
Error
The Schedule From field in Microsoft Project is equal to Project Finish date. Instead, it must be set to Project Start date.
|
Open the Project Information window and set the Schedule From field to the Project Start date.
|
Custom project calendar
|
Error
The project calendar must be one of the following base calendars: Standard or 24 Hours.
|
From the Project Information window, set the project calendar to one of the following base calendars: Standard or 24 Hours, and ensure that the selected base calendar has not been modified.
|
Modified default base calendars
|
Warning
A warning appears if the modified calendar is used as the project calendar. The project calendar must be one of the following base calendars: Standard or 24 Hours.
|
Open the Change Working Time window and remove any modifications that have been made to the base calendars.
|
Hours per day
|
Warning
Custom hours per day is not supported. Work hours must be set to 8 per day.
|
From the Calendar tab of the Options window, set the hours per day to 8.
|
Hours per week
|
Error
Custom hours per week is not supported. Work hours must be set to 40 per week.
|
From the Calendar tab of the Options window, set the hours per week to 40.
|
Days per month
|
Error
Custom days per month is not supported. Work days must be set to 20 per month.
|
From the Calendar tab of the Options window, set days per month set to 20.
|
Unsupported Feature
|
Error or Warning
|
Resolution in Microsoft Project
|
Duration format
|
Error
Elapsed duration is not supported.
|
Change all elapsed duration formats to non-elapsed duration formats.
|
Split tasks
|
Warning
Tasks cannot be split. Resume must equal Stop.
|
The split is ignored upon import.
|
Recurring task
|
Error
A task has been flagged as recurring.
|
Remove all recurring tasks.
|
Subprojects
|
Warning
Subproject dependencies are not supported.
|
A subproject will be imported as a standard activity.
|
Task calendar
|
Error
Task calendars are not supported.
|
Under the Advanced tab of the Task Information window, set Calendar to None.
|
Resource leveling
|
Error
Resource leveling is not supported.
|
Open the Resource Leveling window and clear the leveling for the entire project.
|
Leads and lags as percent
|
Error
Defining a lead or lag as a percent is not supported.
|
Under the Predecessors tab of the Task Information window, remove any leads and lags that are specified as percentages.
|
Cross project dependencies
|
Error
A task has an external dependency. Cross project dependencies are not supported.
|
Remove all cross-project dependencies.
|
Baselines
|
Warning
A baseline attribute contains data. Baselines are not supported.
|
If any baseline attributes have been defined, they are ignored upon import.
|
Actual cost calculation
|
Error
Actual costs must always be calculated.
|
Navigate to
> > and select the checkbox indicating that actual costs are always calculated by Microsoft Project. |
Unsupported Feature
|
Error or Warning
|
Resolution in Microsoft Project
|
Type
|
Error
An activity includes a resource of the type Material or Cost.
|
Under the Resources tab of the Task Information window, remove all usages of material and cost resources.
|
Resource calendars
|
Error
Resource calendars cannot be different than the project calendar.
|
Open the Change Working Time window for the resource and set the base calendar so that it is the same as the project calendar.
|
Baselines
|
Warning
Baseline attributes currently contain data.
|
If any baseline attributes have been specified, they will be ignored upon import.
|
Rate tables
|
Error—If multiple effective rates exist in Rate Table A.
Warning—If multiple effective rates exist in other rate tables.
Yearly rates are not supported.
|
Under the Costs tab of the Resource Information window, remove all but one of the rates from Rate Table A.
All rate information in tables other than Rate Table A will be ignored upon import.
|
Rate format
|
None
|
If the standard rate for the resource is specified as any other format, then rates are recalculated to dollars per hour
|
Unsupported Feature
|
Error or Warning
|
Resolution in Microsoft Project
|
Assignment delay
|
Error
Assignment delays are not supported.
|
From the Task Usage view, add the Assignment Delay column to and set the Assignment Delay to zero.
|
Leveling delay
|
Error
A leveling delay is different from zero.
|
Open the Resource Leveling window and clear the leveling for the entire project.
|
Overtime work
|
Error
Overtime work is not supported.
|
From the Task Usage view, add the Overtime Work column to and set Overtime Work to zero.
|
Work contour
|
Error
Assignment work contours must be Flat.
|
Open the Assignment Information window and set the work contour to Flat.
|
Baselines
|
Warning
Baseline attributes currently contain data.
|
If any baseline attributes have been specified, they will be ignored upon import.
|