Data Management Capabilities > Managing Projects > Projects and Programs > Plan Baselines > Manage Plan Baselines
  
Manage Plan Baselines
Once created, plan baselines are read-only. However, users can set an active baseline, and plan managers can delete baselines.
Setting an Active Baseline
The active baseline is used when comparing how much has changed between baseline versions. By default, the active baseline is information derived from the current plan. For more information, see View Plan Baseline Information.
To set an active baseline, navigate to the Schedule table and click the view information icon next to the plan node. Select the Baselines tab.
From the Plan Baselines table, select the checkbox next to a baseline and then select Actions > Set as Active Baseline.
Delete a Baseline
Plan baselines can be deleted by a plan manager. You can only delete the entire plan baseline; you cannot delete individual objects from a baseline.
To delete a baseline, navigate to the Schedule table and click the view information icon next to the plan node. Select the Baselines tab.
From the Plan Baselines table, select the checkbox next to a baseline and then select Actions > Delete.