Field Name
|
Description
|
Name
|
Specifies the name of the resource. If the resource is a person, it specifies the full name of the person. Resources are created for team members as they are added to the team. If a team member was invited by e-mail address only and has not yet registered, their e-mail address is displayed along with the word PENDING.
|
Actions
|
Lists the available actions. If you are the project or program manager, you can edit and delete resources. This drop-down list is only available to project or program managers.
|
Type
|
Specifies whether the resource is a person, material, equipment, or facility.
|
User
|
Specifies the full name of the user that is associated with the resource.
|
Organization
|
If the resource is a person, this field specifies the organization to which the individual belongs.
|
Standard Rate/hour
|
Specifies the hourly cost of the resource or the cost of the resource per unit of use. If the resource is associated to an activity, the estimated hours and actual hours specified when editing the activity are used to calculate the total cost. The cost amount specified is used in the overall budget calculations which can be viewed on the Details page of the project or program. This information is only displayed to the project or program manager.
|
Cost Per Use
|
Specifies cost per unit or cost per unit time that should be added to the resource cost in addition to the standard rate (if applicable). Only the resource units percentage is added to the cost of the activity.
This field is especially pertinent to facility and equipment resources. For example, if your resource is a piece of equipment, it might have a fee of $100 that is separate from its hourly rate. If you assign that machine as a resource and allocate 50% of its use to that activity, then $50 is added to the activity cost.
|
Max Utilization
|
Specifies the percentage of the extent of the use of the resource. For example, if the resource is a person, this specifies the maximum amount of that person's time that can be dedicated to the project or program.
|