|
In order to import and export plans, your version of Microsoft Project must be compatible with Windchill. For more information, see “Windchill Client Components” in the Windchill 10.1 Software Matrices.
Project or program managers can also exchange plan information between Microsoft Project 2002 and 2003 through the Microsoft Project XML format. This type of exchange is not as seamless but does not require the installation of a plug-in component. Windchill is able to directly import and export the Microsoft Project XML format.
|
Project Item
|
Microsoft Projects
|
Classic Windchill Projects
|
Terms: activity/task/assignment
|
A Microsoft Project task is the same as a Windchill activity.
A Microsoft Project assignment is the same as a Windchill task.
|
A Windchill activity is the same as a Microsoft Project task.
A Windchill task is a work object that is optionally (and automatically) created and delivered to a resource associated with an activity. The creation of tasks is not enabled by default.
|
Milestone behavior
|
Milestones can be associated with child milestones or activities.
|
Milestones cannot be associated with child milestones or activities.
|
Deliverables
|
Deliverable objects are not supported in Microsoft Project.
|
Supports deliverable objects that can be associated with Windchill activities and milestones.
|
Calendar
|
Uses separate calendars associated with the project or program as a whole and with each resource in the project or program
|
Uses a single system calendar for all schedule and cost calculations across all projects or programs and all resources.
|
Duration and effort
|
Combines working days and work effort.
Supports various units for expressing duration and effort.
|
Separates the concept of working days (duration) and work effort.
Activity duration can only be expressed in days, and work effort can only be expressed in hours.
All activities are defined as fixed duration.
|
Resources
|
Exposes overtime rates for resources, and calculates total costs at start or finish.
|
Does not expose overtime rates for resources, and all costs are immediately calculated when entered.
|
Precedence relationships and date constraints
|
Supports multiple precedence relationships and date constraints
|
Supports only finish-to-start (FS) precedence relationships and “start-no-earlier-than” date constraints between activities.
|