Editing a Variance in a Project
You can edit variances in the following ways:
• Select Edit from the actions list on the information page of objects that have variances.
• Select an existing object that has a variance on the Folders page of the Project tab, and select Edit Variance from the actions list.
|
If the selected objects are not available for change, either because they are checked out, or are not able to be changed, an error message displays.
|
The Edit Variance window divides the editing of a variance into the following steps:
1. Set Attributes — For providing the descriptive attributes associated with the variance.
2. Define Impact — For commenting on the effect the variance will have on schedules, cost, and so on.
3. Select Affected Objects — For identifying the affected objects that are involved with the variance. Only those objects that are shared to the same project can be selected.
4. Set Attachments — For managing associated file attachments. Files in the context of the variance can be added, updated, deleted, or viewed.
|
Steps do not necessarily need to be completed in the order in which they are listed. You may navigate to any step for which the link is enabled.
|