Closing a Change Package
 
si closecp
Once the necessary changes are made to the members and subprojects, and they are committed to the repository, you can close the change package by selecting Change Package > Close.
In addition to this procedure, you can close a change package in the GUI by selecting the Close Change Package option when performing member or subproject operations.
If workflows are enabled, closing a change package allows the item to move forward in the PTC RV&S workflow.
* 
You can only close a change package that you have created unless you have administrator permissions.
If reviews are mandatory, you cannot close a change package. It must follow the review process and be closed by the PTC RV&S server.
Was this helpful?