Creating and Changing Process Plans
To create or change process plans in your SAP distribution targets, the following are assumed:
Associated Operation Work centers exist in SAP.
The following mappings for time are based on the default AP Workcenter 1100
Setup time — Standard value: 1; and Standard unit: 1
Processing time — Standard value: 2; and Standard unit: 2
Labor time — Standard value: 3; and Standard unit: 3
This mapping needs to be customized based on the workcenter and plant configuration.
When Process Plans are published to SAP, the associated BOMs, operations, sequences and control characteristics are also published. Resources allocated to operations are published as well; however, skills are ignored by the middleware business logic.
Documents associated to operations and resources are published, but those associated to process plans and sequences are ignored by the middleware business logic.
A CN with Parametric effectivity, such as serial effectivity, is not supported for Process Plan publication.
A standard sequence must have a branching and returning operation.
Labels of operations that occur in a parallel sequence must fall in the range between the branching and returning operations.
By default Process Plans are published with a status of 4 (Released)
Sub-operations are supported only up-to one level. This means a sub-operation cannot have a sub-operation within itself.
The middleware throws an exception for the following conditions:
IsStandard flag is set to true
Multiple versions for the same part are published in a single transaction
Component of a phantom BOM is allocated to a Routing operation
BOM is a Phantom CAD subassembly