Collecting Routing Plan and Associated Localized Operations
Use the Collect Localized Operations for Routing Plan preference to automatically collect the localized operations along with the routing plan. The available values for this preference are All and None (default). When set to None, only the routing plan is collected. When set to All, the routing plan and the associated localized operations are collected.
Another way of collecting the routing plan and its associated localized operations is by using the
Collect Consuming Localized Operations action available in the
Advanced Add dialog box. The
Advanced Add dialog box opens when you click the
Advanced collection action in the collector locations. The
Advanced collection action is available at the following collector locations:
• Revise
• Add to Baseline
• Display related manufacturing objects
• Set state
• Move
• Promotion request
• Variance
• Problem Report Collector
• Change Request Collector
• Change Notice Collector
Using the Collect Localized Operations for Routing Plan Preference
1. Consider that a routing plan RP1 has three localized operations associated with it. The Collect Localized Operations for Routing Plan preference value is set to All.
2. Open the information page of RP1.
3. Click > . The Set State dialog box opens, showing the routing plan and its associated localized operations on the Object List table.
| In this case, it is not required to use the Collect Consuming Localized Operations action . |
Using the Collect Consuming Localized Operations Action
1. Consider that a routing plan RP1 has three localized operations associated with it. The Collect Localized Operations for Routing Plan preference value is set to None.
2. Open the information page of RP1.
3. Click > . The Set State dialog box opens, showing only the routing plan on the Object List table. The localized operations do not appear as the value of the Collect Localized Operations for Routing Plan preference value is set to None.
4. To collect the associated localized operations, select the routing plan RP1 in the Object List table.
5. Click
Advanced collection. The
Advanced Add dialog box opens.
6. Select the Collect Consuming Localized Operations checkbox and click OK. The Advanced Add dialog box closes, and the localized operations are collected in the Object List table.