The Estimated incorporation date can be set to any date.
|
|
The following criteria apply to setting the Start incorporation date:
• Can only be set if all child part instances have been allocated and incorporated.
• Must be today’s date or earlier.
• Cannot be set to a date within the start/end date range of a previous part instance version.
|
|
Once you have recorded a Start incorporation date the Estimated incorporation date field disappears from this window and the End incorporation date appears. To reset the Estimated incorporation date you must clear the Start date. The next time the Set Incorporation action is taken the Estimated and Start incorporation dates reappear and the Estimated date may be redefined.
|
|
The following criteria apply to setting the End incorporation date:
• The End incorporation date must be later than the Start incorporation date.
• The Start date may not be cleared once the End date is set.
|