Element | Description |
---|---|
ObjectHeader | Description is as per BOM schema. |
WCID | Unique identifier for the Process Plan Operation; internal to Windchill MPMLink. |
OperationNumber | Operation number from Windchill. This is not mapped in Oracle but used as a unique identifier for operations in the business logic. |
OperationSequenceNumber | Operation label, mapped to Operation sequence number in Oracle. This is a unique attribute for operation in Oracle. |
OldOperationSeqNumber | Contains the old value of the operation label. |
ProcessPlanPartNumber | PartNumber from ProcessPlanPartLink, from Windchill. |
Description | Description of the operation, from Windchill. |
Department | Department specified in the work center link for the operation. |
Scheduled | Default is true. This flag will be used for the resources which are created for the work center link. |
OldScheduled | Old value of the scheduled flag defined for the operation. |
NewSetuptime | Current set up time defined on the operation. The default unit of time is seconds. The default in Oracle is to use this as timing for the activity Prerun. |
NewProcessingTime | Current processing time defined on the operation. The default unit of the time is seconds. The default in Oracle is to use this as timing for the activity Run. |
NewTeardownTime | Current tear down time defined on the operation. The default unit of the time is seconds. The default in Oracle is to use this as timing for the activity Postrun. |
NewQueueTime | Current queue time defined on the operation. The default unit of the time is seconds. The default in Oracle is to use this as timing for the activity Queue. |
NewWaitingTime | Current queue time defined on the operation. The default unit of the time is seconds. The default in Oracle is to use this as timing for the activity Move. |
OldSetuptime | Old value of the set up time defined on the operation. |
OldProcessingTime | Old value of the processing time defined on the operation. |
OldTeardownTime | Old value of the tear down time defined on the operation. |
OldQueueTime | Old value of the queue time defined on the operation. |
OldWaitingTime | Old value of the waiting time defined on the operation. |
Quantity | Quantity from the Windchill. |
Effectivity_Old | Old effectivity value fetched from the Oracle in case of change in operation. |
Effectivity | Contains the sub element StartDate. From when the Process Plan (Routing in Oracle) revision will be effective. |
OperationLinkUserArea | This field can be used for the customization. |