Windchill supports both MPP and XML files. You can only select XML files that were generated according to the Microsoft Project 2003, 2007, or 2010 XML format.
|
![]() |
Selecting Replace also removes objects that are not supported in Microsoft Project. For example, any deliverables included in your plan will be deleted.
If you are importing a plan using Replace mode, then the reference to the subplan is dropped.
|
![]() |
• If you are importing a plan created in Microsoft Project, ensure that all activities have their task mode set to Auto Scheduled. Activities with the Manually Scheduled mode will be auto-scheduled when imported back into Windchill ProjectLink, which might create confusion.
• The actual start date in the Microsoft Project plan should match the actual start date in Windchill or a later date. The import fails if the actual start date in Microsoft Project plan is prior to the actual start date in Windchill. • When a manual plan is started using the ![]() |