Creating the Change Baseline Report
The Change Baseline report summarizes the change history and any anticipated changes to a released product. With this report, you can see the current released product structure as well as any pending changes against objects within that product structure. You can generate the report from any part.
* 
In order to expose the Change Baseline report, the Change Baseline Report Display preference in the Preference Management utility must be enabled.
Use the following procedure to generate the Change Baseline report:
1. From the information page of a part, select the Structure tab.
2. Define the appropriate expansion criteria.
3. From the actions toolbar, click Reports and select Change Baseline.
4. The Change Baseline Report window appears.