Microsoft Project Integration
Members of a project, product, or program who have the necessary permissions to create and edit plan objects can import and export plans between Microsoft Project and Windchill. This allows you to edit plan information within Microsoft Project and then save it to the Windchill plan.
* 
To import and export plans, your version of Microsoft Project must be compatible with Windchill.
If the Microsoft Project plugin fails to function, check your config.xml file. The LogLocation attribute must be defined with a valid directory name. You must also have create and edit permission within the directory location.
This is necessary to save any errors or warnings generated by the Windchill server.
* 
The Microsoft Project plugin is not supported in a single sign-on (SSO) environment. You need to import plans using the Windchill UI. For more information on importing plans, see Import a Microsoft Project Plan.
Differences Between Microsoft Project Plans and Windchill Plans
Microsoft Project
Windchill Project
Terms
Task
A Microsoft Project “task” is the same as a Windchill activity.
Assignment
A Microsoft Project “assignment” is the same as a Windchill task.
Activity
A Windchill activity is the same as a Microsoft Project “task.”
Task
In Windchill, a task is a work item is assigned to users either automatically or as part of a generated workflow. For more information, see Managing Your Tasks.
Milestone behavior
Milestones can be associated with child milestones or activities.
Milestones cannot be associated with child milestones or activities.
Deliverables
Deliverable objects are not supported in Microsoft Project.
Windchill deliverables are objects that can be associated with activities and milestones. For more information, see Deliverables.
Calendar
Uses separate calendars associated with the project or program as a whole and with each resource in the project or program
Uses a single system calendar for all schedule and cost calculations across all projects or programs and all resources.
Resources
Exposes overtime rates for resources, and calculates total costs at start or finish.
Does not expose overtime rates for resources, and all costs are immediately calculated when entered.
For a detailed list of Microsoft Project features that are not supported in Windchill, see Unsupported Import Features.