PTC FlexPLM Fundamentals > Season Dashboards > Task Colors > Incomplete Products or Colorways
  
Incomplete Products or Colorways
The system assigns a color to a product or colorway task when a product or colorway is not complete.
Task Color
Logic
Red
The estimated end date of the season task in the header is before the current date. This color indicates that the task is currently late.
Yellow
The estimated end date of the product or colorway task is after the estimated end date of the season task. This color indicates that the task will most likely be late if the tasks finish with the entered duration.
Green
The estimated end date of the product or colorway task is before the estimated end date of the season task. This color indicates that the task will most likely finish early or on time.