Task Color
|
Logic
|
Red
|
The estimated end date of the season task in the header is before the current date. This color indicates that the task is currently late.
|
Yellow
|
The estimated end date of the product or colorway task is after the estimated end date of the season task. This color indicates that the task will most likely be late if the tasks finish with the entered duration.
|
Green
|
The estimated end date of the product or colorway task is before the estimated end date of the season task. This color indicates that the task will most likely finish early or on time.
|