PTC FlexPLM Fundamentals > Costing > Costing From the Line Sheet > Working With Cost Sheets from the Line Sheet > Changing Primary Sources
  
Changing Primary Sources
When viewing the cost sheet from the line sheet, you can designate the associated source of a cost sheet as the primary source for both the associated product and the associated season.
Displaying All Sources
Before you can change primary product and season sources, you must first display all sources. To display all sources, do the following:
1. Click Options to display the Line Sheet Viewer Options box. The Line Sheet Viewer Options box includes checkboxes for including all sources, all active cost sheets, and all what if cost sheets.
2. Select the Include All Sources checkbox to be able to change primary sources.
To include active cost sheets, select the Include All Active Cost Sheets checkbox.
To include what if cost sheets, select the Include What If Cost Sheets checkbox.
You can select both checkboxes to display both types of cost sheets.
3. Click Run to view the updated line sheet.
Setting a Primary Product Source
From the Actions menu of the cost sheet whose source you want to set as the primary source for the product, select Set as Primary (Product).
* 
This option does not appear if the source is already the primary product source.
Selecting this option sets the corresponding source as the primary source for the corresponding product. The system refreshes and returns you to the Line Sheet Viewer.
Setting a Primary Season Source
From the Actions menu of the cost sheet whose source you want to set as the primary source for the season, select Set as Primary (Season).
* 
This option does not appear if the source is already the primary season source.
Selecting this option sets the corresponding source as the primary source for the product and season combination for the given cost sheet. The system refreshes and returns you to the Line Sheet Viewer.