Setting up a SYNERGY/CM project to work with Modeler - with SYNERGY/CM (CM tool integration)
* 
CM tool integration support for Telelogic SYNERGY/CM is being deprecated.
1. If you have not done so already, set up the SYNERGY/CM database to work with Modeler. See Setting up a SYNERGY/CM database to work with Modeler - with SYNERGY/CM.
2. If you are using SYNERGY/CM version 6.3:
a. Ensure that you use the ccm_admin role when creating the project.
b. Ensure that the name of the project does not contain any spaces.
c. Set the project's Purpose to Shared. Note that when you create a Project in SYNERGY/CM, its Purpose is set to Personal by default and it cannot be changed after creation.
* 
A CM project can store only one Model.
3. Define the Project's Work Area Directory using a UNC path. On the Work Area Properties dialog, you must type the UNC path in the Directory box. For example:
If you want SYNERGY/CM to create a work area in a subfolder of the c:\ccm_wa folder on a computer whose machine name is computer12, create a share for the ccm_wa folder (named ccm_wa in this example) and type the following text in the Directory box:
\\computer12\ccm_wa\
4. Close the Create Project dialog.
5. If you are using SYNERGY/CM version 6.3, from SYNERGY/CM, set the Status of the project's Directory object to Integrate or Public. Note that by default the status of the directory object is set to working, which prevents non-owners of the directory object from checking in new Packages.
After setting up SYNERGY/CM, you can check in a Modeler Model. For more information, see Checking in a model the first time - with SYNERGY/CM.