Coordinate Measuring Machines (CMM) > Verify Steps > The CMM VERIFY Dialog Box > About the CMM VERIFY Dialog Box
  
About the CMM VERIFY Dialog Box
The following elements are common for all Verify steps:
Name—Supply a meaningful name for the step, to be used in namelist menus and system messages. This element is optional. If you do not supply a name, the step will have a default name generated by the system (for example, "10: VER01, Operation: OP010").
Tolerance—Select a dimension or geometric tolerance to verify.
Feature(s)—The measured or constructed entity, or entities, that the dimension or gtol controls.
Datum(s)—The measured or constructed entity, or entities, that the dimension or gtol is based upon.
Ref Csys—Change the coordinate system to be used as reference for this Verify step.
Comment—Enter comment to be output before the DMIS block for the step. This element is optional.