To Perform Line Balancing
You can perform line balancing by using the Process Graph dialog box. You can also verify the limits for reordering a step directly in the Process Table.
1. Select a step in the Process Table and click .
2. Creo NC checks the step dependencies (parent child relation), and indicates the limits of its possible reordering in the Process Table (the top and bottom lines) by highlighting them in red. If a bottom limit does not exist, you can insert the step anywhere below the top limit line. You can then reorder the step to a new position within these limits by using the Cut and Paste functionality.
* 
You can copy or move a step to anywhere within the table before applying the step to the Process Table. However, after you apply a step to the Process Table, the step can be reordered only within an operation.