Exporting Story Points
During export the Story points assigned to Codebeamer work items can be converted to the duration hours in MS Project. This conversion only happens if you enter a ratio of how many hours is a story point worth in the Convert Story Points to hours field during export:
For example, if you enter 4 in the Convert Story Points to hours field, each story point is translated into 4 hours when the data is exported to MS Project.
|
|
Story Points are only converted if the exported work item's Estimate Hours field is empty. The value of this field is not overridden in MS Project.
|