Codebeamer field
|
MS-Project field
|
---|---|
ID
|
Hyperlink (inside hyperlink)
|
Description
|
Note
|
Name
|
Task name
|
Start Date
|
Task Start date
|
End Date
|
Task Finish date
|
Estimated Hours
|
Duration
|
Spent Hours
|
Actual Duration, also % Complete is calculated automatically
|
Priority
|
Priority
|
Assigned To
|
Resources are created and assigned from users and roles
|
Story Points
|
Optionally converts Story Points to Duration if the Estimated Hours is not set. The conversion rate is configurable.
|