Settings | default value | An example |
---|---|---|
Hours per day | 8 hours | Example: 1.5 days means 12 hours |
Hours per week | 40 hours | Example: 2 weeks means 80 hours |
Days per month | 20 days | Example: 1.5 month means 30 workdays, which means 30*8=240 work hours |
![]() | The Planned Effort and Spent Effortfields are calculated fields in Codebeamer and may change when you update a work item of the imported items. However, the importer willdisable these calculations during import to get the same values calculated by MS Project. If you don't want these fields overwritten by Codebeamer, reconfigure the tracker and disable propagation and calculation for these fields. |