Converting Between MS-Project Durations and Hours in Codebeamer
In MS-Project, the task durations can be set to values such as 1 day, 1 week, 1 month. These values mean one workday (8 hours) or one work week (5 days).
For an approximate conversion from the MS-Project durations, such as 1 day, select the duration from the settings in the MS-Project file. These can be found by clicking the File > Options menu inside MS-Project and then clicking Schedule.
The following values can be configured:
Settings
default value
An example
Hours per day
8 hours
Example: 1.5 days means 12 hours
Hours per week
40 hours
Example: 2 weeks means 80 hours
Days per month
20 days
Example: 1.5 month means 30 workdays, which means 30*8=240 work hours
The same values are configurable during MS-Project export, which puts these values into the export file.
* 
The Planned Effort and Spent Effortfields are calculated fields in Codebeamer and may change when you update a work item of the imported items. However, the importer willdisable these calculations during import to get the same values calculated by MS Project. If you don't want these fields overwritten by Codebeamer, reconfigure the tracker and disable propagation and calculation for these fields.