Data Management Capabilities > Managing Plans > Plan Baselines > Create a Plan Baseline
  
Create a Plan Baseline
You can create a plan baseline from the Schedule table and from the plan information page:
Navigate to the Schedule table and select Actions > New Plan Baseline.
Navigate to the plan information page and select the Baselines tab.
From the Plan Baselines table, select Actions > New Plan Baseline.
From the New Plan Baseline window, provide a name and description for the baseline. Click OK.
A baselined version of all current plan objects is created.