Child Activity
|
Start
|
Finish
|
Duration
|
Work
|
% Work Complete
|
Activity 1
|
01-06-2017
|
01-17-2017
|
10 days
|
50 hours
|
100%
|
Activity 2
|
01-15-2017
|
01-24-2017
|
8 days
|
30 hours
|
75%
|
Activity 3
|
01-09-2017
|
02-05-2017
|
20 days
|
80 hours
|
25%
|
Activity 4
|
01-08-2017
|
01-10-2017
|
3 days
|
10 hours
|
100%
|
|
The duration is the number of working days between the start and finish dates. This example uses a work week that extends Monday through Friday, with 40 hours of work per week.
|
Start
|
Finish
|
Duration
|
Work
|
% Work Complete
|
01-06-2017
|
02-05-2017
|
23 days
|
170 hours
|
60%
|
(Child Activity Work ÷ Total Work) * 100 = Percent of work that the child activity represents |
(10 ÷ 170) * 100 = 5.8 |